Brownsberger update: Conservation issues in Alewife area
September 29th, 2008The following is a summary of a meeting that occurred at the State House (Sept. 25) regarding the status of Department of Conservation and Recreation issues in the Alewife area, as reported by Rep. Will Brownsberger in an e-mail update on Sept. 29. It is republished here with his permission.
There is a lot going on, and I’m grateful to Commissioner Rick Sullivan for his continuing attention to a wide range of concerns.
The Silver Maple Forest issue was not a central topic in the meeting, although we touched on it briefly — that issue has been directed up at the level of the Governor’s office. Another issue which was not on the table in the meeting is traffic improvements at the Rt.2/Rt.16 intersection. I continue to follow up on both of those issues and will report separately on them.
Present (for all or part of the meeting):
From DCR:
Commissioner Sullivan
Samantha Overton (Urban Parks)
Dan Driscoll (Planning)
Bill Gode (Flood Control)
Mike Galvin (Engineering)
Rosemary Power (Government Relations)
Legislators and others
Senator Pat Jehlen
Senator Steven Tolman
Representative Will Brownsberger
Representative Sean Garballey
Representative Denise Provost
Selectman Clarissa Rowe
Ken Donnelly
Cindy Friedman (Senator Marzilli)
Robert Fitzpatrick (Senator Jehlen)
Mike Rademacher (Arlington Town Engineer)
Alewife Reservation Master Plan Status
The plan is partially implemented in the area of the Arthur D. Little parking lot, but waiting for Cambridge CSO work in the area across Little River from the lot. The Uplands acquisition was vetoed by the Governor and in the absence of the vetoed funds DCR does not feel it has the financial ability to acquire the property. Legislators and local officials continue to look for ways to save both the Silver Maple Forest and the Mugar property. Implementation of the plan in the area towards Little Pond will occur as a later phase.
Regarding the proposed bikepath segment in the Sunny-side area, DCR is planning to organize conversations with Arlington officials this fall to resolve differences about the location of the bike path.
Amelia Earhart Dam
DCR feels that the 2008 and ‘09 budget earmarks for study of the dam suffice to move an appropriate study forward to address (a) the feasibility and cost of installing a fourth pump; (b) the feasibility and advisability of changing pumping protocols at the Amelia Earhart to control flooding. DCR expects to have an RFP out on this next month and will send it to legislators for review before issuing it.
Mystic Lakes Dam
DCR is well along in designing a repair and reconstruction of the Mystic Lakes Dam. This project is necessary for safety reasons — the dam is weak. It will also create a fish ladder and allow active management of the upper lake for flood storage purposes. They hope to put out an ENF [environmental-enforcement action] before the end of the year. One inevitable negative to the reconstruction will be the removal of trees on the dam. The trees on the dam are all volunteers and their roots create faults in the dam which diminish its strength. It is expected that construction will start in Fall 2009 and take approximately two years.
Dredging and Debris Removal in the Little River and Alewife
The ongoing concern about maintaining a free flowing channel is very well recognized both by the stormwater group (Robert Lowell) and by the Urban Parks group (Samantha Overton). Currently, they are testing the materials in the channel bottom to identify possible hazardous materials (including sharps from the homeless population) and to define the process to be used in debris clearance and/or dredging. They do not feel that they can order large crews of people to work standing in the channel, even for branch removal, before assessing risks. They expect to make findings over the next few weeks and to define a course of action from there.
Blair Pond sedimentation project (dredging and control structure)
They are currently doing depth mapping to design their approach to dredging the pond. lt may or may not be possible to simply move materials within the pond as opposed to trucking materials off site. This will afffect permitting issues and the timeline. No deadlines were set, but the work appears to be moving forward.
McCrehan Pool
It was agreed that DCR would review the possibility of allocating staff resources to participate in visioning conversation about the pool — to inventory short term to do’s as well as longer term possible goals.
Belmont Bikepath Right-of-Way Issues
The transfers and easements to create the right-of-way for the Belmont to Alewife bike path are all approved by the grantors. The actual documentation received has to be approved by both EoEEA and DCAM. The General Counsel of DCR is attending to the movement of the documents through these approvals.